Drivers in Santa Maria are advised that temporary delays will occur during the day on Jones Street and Bradley Road, and at night on Bradley Road, due to the city’s Pavement Repairs Project.
The repairs are set to begin Wednesday, July 10 on Jones Street between College Drive and Bradley Road through the end of July, weather permitting.
Following the Jones Street work, the contractor will move to Bradley Road and continue south.
It is recommended that motorists use alternate routes when possible if traveling between 7 a.m. and 4 p.m. on Jones Street or Bradley Road between Jones Street and Stowell Road; and from 8 p.m.-5 a.m. on Bradley Road between Stowell Road and Betteravia Road.
The project will include the removal and replacement of old and failed asphalt paving; removal of existing traffic striping; grinding of the edges of the existing pavement; placement of hot mix asphalt overlay; then re-establishment of traffic striping.
The city has contracted Main Line Engineering Construction Inc. to perform the work funded by Measure A, Gas Tax, and SB-1 Gas Tax dollars.
As one of its Smart City, Safe City tools, the Santa Maria Department of Public Works tracks the Pavement Condition Index (PCI) to assess the condition of streets.
Based on available funds, including tax revenue from gas purchases, staff conducts annual assessments and develop road projects.
Street segments that are part of these pavement repairs include:
• East Jones Street from South College Drive to South Concepcion Avenue
• East Jones Street from South Concepcion Avenue to South Bradley Road
• South Bradley Road from East Jones Street to Sierra Madre Avenue
• South Bradley Road from Sierra Madre Avenue to East Stowell Road
• South Bradley Road from East Stowell Road to East Battles Road (night work)
• South Bradley Road from East Battles Road to Betteravia Road (night work)
The contractor will post construction notices to residents and businesses along affected streets with the dates, informing when parking and access to streets will be prohibited.
City staff recommend drivers obey all temporary construction signs and reduce driving speeds in construction areas.
Direct questions to the Department of Public Works, engineering division, 805-925-0951 ext. 2225.