Drivers are advised that temporary delays and reduction in vehicular lanes will occur for the next two months on Stowell Road and Miller Street for a storm drain installation project in Santa Maria.
The repairs are set to begin Tuesday, Sept. 3.
The work on Stowell Road is expected to take one month to complete, and the work on Miller Street is expected to be completed in one month, with an anticipated completion date for the project of Nov. 1, according to the city of Santa Maria.
For safety reasons, some work may occur at night, the city said.
The project will include trenching, storm drain installation, and roadway restoration.
The work is being performed by Kirk Construction, a contractor working on behalf of the Centennial Square development at the southwest corner of Miller Street and Plaza Drive.
The contractor will post construction notices to residents and businesses along affected streets with the dates, informing them when parking and access to streets will be prohibited.
City staff recommends drivers obey all temporary construction signs and reduce driving speeds in construction areas.
Direct questions to the Department of Public Works, engineering division, 805-925-0951 ext. 2225.