The western leg of Baseline Avenue/Edison Street will be closed at its connection to Hwy. 154 beginning Tuesday, Sept. 3, as the final portion of a detour is completed for an ongoing roundabout construction project.

A new traffic alignment on Hwy. 154 at the intersection of Baseline Avenue/Edison Street will begin Friday, Sept. 6 and run through February 2025.

Businesses will remain open and accessible along Baseline Avenue/Edison Street during construction. Message and directional signs will be in place to alert the traveling public of detours.

Work includes the construction of a roundabout at the intersection of Hwy. 154 and Baseline Avenue/Edison Street, installation of curb ramps, rumble strips and a lighting system. 

The roundabout project is expected to be complete in spring 2025.

Contractor for the $8.7 million project is Granite Construction Company of Santa Maria.